FULL/2025/1774 planning application

Site adjacent to Tabor Le Feugre Castel Guernsey GY5 7TY · Castel

What is proposed

Demolish building and erect 2 dwellings with associated works.

Demolish & rebuild dwellingDemolition
Est. cost of works: £2,750–£4,000 per m² of new build (total depends on floor area — not stated in the planning record)
Status
Granted
Received
Decision date
Time to decision
46 days
Applicant
Torode Developments
Agent
Private individual

Official record
Decision notice (PDF)

Source: States of Guernsey Planning Websearch. Dates and description reproduce factual register fields. Private individuals are not named here. Check the official record before relying on this page.