FULL/2024/1182 planning application

St Andrews Community Centre LBG Rue de la Boullerie St. Andrew Guernsey GY6 8XD · St Andrew

What is proposed

Repair retaining wall and install sleeper wall to west boundary.

Boundary / access works
Est. cost of works: £6,250–£18,750
Worked on by: BTP Limited
Status
Granted
Received
Decision date
Time to decision
61 days

Official record
Decision notice (PDF)

Source: States of Guernsey Planning Websearch. Dates and description reproduce factual register fields. Private individuals are not named here. Check the official record before relying on this page.